Central Miramar

Project Map
Select the red dots on the following map for project details:
Bond Dollar Locations Map_Mar2016_988
17 19 18 15 16 8 7 6 9 14 10 12 11 13 5 4 3 1 2

6 - Adult Daycare Center

8915 Miramar Parkway
Miramar, FL 33025

Current Status


Construction
    

Project Scope


Construction of a one story 3,800 sq. ft. Adult Daycare Center to be built at the site adjacent to Fire Station 70. The facility includes a warming kitchen, dining room, classroom/meeting room and office support areas.

Project Details

Topic Detail
Total Project Budget
$2,006,385
Funding From Revenue Bond
$1,400,000
Funding from other sources $606,385
Construction Start Date
November 2015
Estimated Construction Completion Date
October 2016
AdultDayCareRendering2

7 - Forzano Park - Phase II

2001 S. Douglas Road 
Miramar, FL 33025

Current Status


Construction Contract Awarded


Project Scope


Includes the expansion of the parking area as well as landscape and irrigation improvements.

Project Details

Topic Detail
Total Project Budget
$845,000
Funding From Revenue Bond
$800,000
Funding from other sources 45,000
Estimated Construction Start Date
August 2016
Estimated Construction Completion Date
February 2017
ForzanoParkPhaseII

8 - Lakeshore Park


8501 S. Sherman Circle
Miramar, FL 33025

Current Status


Design
 

Project Scope


Addition of playground and pavilion, removal of excess parking to create open play green areas.

Project Details

Topic Detail
Total Project Budget
$618,545
Funding From Revenue Bond
$300,000
Funding From Other Sources
$318,545
Estimated Construction Start Date
October 2016
Estimated Construction Completion Date
April 2017
Lakeshore Park Layout

9 - River Run Park

9400 Miramar Boulevard
Miramar, FL 33025

Current Status

 
Construction 
  

Project Scope


Additional parking, walking trail improvements, new lighting, conversion of existing storage building into new Community Meeting Room and replacement of existing exercise stations with new.

Project Details

Topic Details
Total Project Funding
$889,500
Funding From Revenue Bond
$600,000
Funding from other source $289,500
Construction Start Date
January 2016
Estimated Construction Completion Date
August 2016
RiverRunParkUpdated_March2016
10. Miramar Police Headquarters
Miramar Town Center - Block 3

Current Status 
Completed
 
Project Scope
New 65,000 sq. ft. 3-story building.  The new facility will accommodate various operational functions including the Command Center, Patrol Division, Special Operations, Records and Internal Affairs.

Project Details

Topic
Detail
Total Project Funding
$28,595,753
Funding From Revenue Bond
$16,845,000
Funding From Other Sources
$11,750,753
Construction Start Date
January 2015
Construction Completion Date
June 2016
Miramar Police Headquarters

11 - Fire Station 107

11811 Miramar Parkway
Miramar, FL 33025

Current Status


Design
  

Project Scope

New three apparatus bay station, office space, and support areas; approximately 13,500 sq. ft.

Project Details

Topic Detail
Total Project Budget
$5,870,521
Funding From Revenue Bond
$4,103,886
Funding From Other Sources
$1,766,635
Estimated Construction Start Date
November 2016
Estimated Construction Completion Date
November 2017
Fire Station 107

12 - Monarch Lakes Park

South of Pembroke Road and West of Southwest 136th Avenue
Miramar, FL 33027

Current Status


Design

Project Scope


Passive park with restrooms, pavilion, walkways connecting adjacent Flamingo Estate Park, lighting and butterfly garden.

Project Details

Topic Detail
Total Project Budget
$1,400,000
Funding From Revenue Bond
$1,300,000
Funding From Other Sources
$100,000
Estimated Construction Start Date
November 2016
Estimated Construction Completion Date
June 2017
MonarchLakesPark
13 - Vizcaya Park Phase III
14200 SW 55th Street 
Miramar, FL 33027
  
Current Status
Completed

Project Scope
Construction of additional soccer field, grass parking, two pavilions, splash pad, new gate and monument sign at Park entrance.

Project Details

Topic Detail
Total Project Budget
$1,779,732
Funding From Revenue Bond
$1,043,978
Funding From Other Sources
$735,754
Construction Start Date
April 2015
Construction Completion Date
December 2015
VizcayaParkIII

14 - Ansin Sports Complex Phase III


10801 Miramar Boulevard
Miramar, FL 33025
 

Current Status


Design
  

Project Scope


Lighting, Sports Field, Walking Trail and Drainage improvements.

Project Details

Topic Detail
Total Project Budget $1,250,000
Funding From Revenue Bond $550,000
Funding from other source $700,000
Estimated Construction Start Date October 2016
Estimated Construction Completion Date May 2017
Ansin with Practice Track