City Wide

Project Map
Select the red dots on the following map for project details:
index_map_050615
25 24 21 22 23 26 14 16 13 15 17 18 19 12 20 11 8 9 10 3 1 2 5 4 6 7
Facilities Capital Improvement
City Wide

Current Status
Design

Project Scope
Preparation of condition assessments of City owned Facilities; development of a 5 year maintenance plan; and Market Value Appraisal.  Assessment report will detail upgrades required at the various facilities throughout the City.  Repair/renovation work will be initiated based on critical need and available funds.  Independent timelines for completion.

Project Details

Topic Detail
Total Project Budget
$700,000
Funding From Revenue Bond
$700,000
Estimated Construction Start Date
Varies
Estimated Construction Completion Date
Varies
FacilitiesCapitalImprovement

Project Details

Topic Detail
Total Project Budget

$1,000,000

Funding From Revenue Bond
$300,000
Funding From Other Sources
$700,000
Estimated Construction Start Date
To be determined
Estimated Construction Completion Date
To be determined
LandscapingAndBeautification