Historic Miramar

Project Map
Select the red dots on the following map for project details:
Bond Dollar Locations Map_Mar2016_988
17 19 18 15 16 8 7 6 9 14 10 12 11 13 5 4 3 1 2

15 - Historic Public Safety Complex

6920 SW 35th Street
Miramar, FL 33023

Current Status

Consultant Selection

Project Scope

This new 24,000 sq. ft building complex includes a variety of key public safety functions at a central city location. The proposed site in Historic Miramar will accommodate the Historic District Police Substation, Logistics, Crime Scene, Evidence Storage and other related functions at one central location.

Project Details

Topic Detail
Total Project Budget
$5,295,837
Funding From Revenue Bond
$4,405,874
Funding From Other Sources
$889,963
Estimated Construction Start Date
March 2017
Estimated Construction Completion Date
April 2018
HistoricPublicSafetyComplex

16. Fairway Park - Lighting

3700 Largo Drive
Miramar, FL 33023

Current Status


Completed
  

Project Scope


Removal of existing light poles, installation of new LED light poles and required wiring that provide enhanced lighting throughout the park.

Project Details

Topic Detail
Total Project Budget
$336,548
Funding from Revenue Bond

$300,000

Funding from Other Sources

$36,548

Construction Start Date
May 2015
Construction Completion Date
December 2015
FairwayParkLightingPlan
17 -  Historic Miramar Complete Streets
State Road 7/441 to SW 62nd Avenue  and
from Pembroke Road to County Line Road

Current Status
Project scope under review by Broward County
   
Project Scope
Phased installation of new sidewalks, pedestrian lights, ADA-access ramps, sod, and native landscaping.

Project Details

Topic Detail
Total Project Budget $1,797,675
Funding from Revenue Bond $200,000
Funding from Other Sources $1,597,675
Estimated Construction Start Date To be determined
Estimated Construction Completion Date To be determined
HistoricMiramarCompleteStreets

18 - Historic Downtown Revitalization


Miramar Parkway between SW 68th Avenue and SW 69th Way

Current Status


Planning

Project Scope


Streetscape improvements such as lighting, crosswalks, landscaping, pavers and drainage.

Project Details

Topic Detail
Total Project Budget $1,850,00
Funding from Revenue Bond $1,350,00
Funding from Other Sources $500,000
Estimated Construction Start Date February 2017
Estimated Construction Completion Date December 2017
HistoricDowntownRevitalization

19 - Historic Miramar Canal Improvements


City-owned canals east of University Drive

Current Status

 
Construction Contracts Awarded
    

Project Scope

 
Restoring integrity of canal banks along City-owned canals.

Project Details

Topic Detail
Total Project Budget
$599,067
Funding From Revenue Bond
$300,000
Funding From Other Sources
$299,067
Estimated Construction Start Date
July 2016
Estimate Construction Completion Date
October 2018