West Water Treatment Lab and Office Space

Expansion of laboratory, office space, and general building at the West Water Treatment Plant.  

February 2019 -  State is awaiting a new proposal for redesign/value engineer of laboratory in order to make a decision on what the next steps will be for this project.

January 2019 - Both contractors were invited to meet with staff to discuss potential VE ideas and reasons why their bids were so much higher than our Architects estimate. Staff has since met with both and now will consider redesign of some project elements in consultation with the Architect. An Amendment to their contract will be necessary for additional design services. 

December 2018 - Project advertised for bids and bids were opened the week of 11/19/18 with results that doubled the estimate. Project under review.  

November 2018 - The bids were extended from October 31, 2018 to November 7, 2018. Staff will work with Procurement to review and process the bids. Staff will schedule the item for award at one of the January 2019 Commission meetings.   

October 2018 - Advertisement for bid is scheduled for September 30, 2018. The Architect proposal to cover the lab equipment in the mechanical yard layout was reviewed and was not accepted.